CalculatorBoom

Concrete Needed for a 12 x 24 ft Slab at 6 Inches

Cubic yards, weight, and premix bags required. Use the calculator below to try your own dimensions.

How deep the slab is poured. 4 inches is standard for patios and walkways; 6 inches or more for driveways.
The bag size you plan to buy — used to estimate how many bags you'll need.
Ready-mix delivered concrete price per cubic yard, if you're having concrete delivered rather than mixing bags yourself.
$

Concrete Needed

Example

A 12 × 24 ft slab at 6" thick needs 5.33 cu yd of concrete (144.0 cu ft), weighing about 10.80 tons — that's 240 bags of 80 lb premix. By the cubic yard, that costs about $800.00.

Volume

144 cu ft

Weight

10.8 tons

Premix Bags Needed

240 bags

Estimated Cost (Delivered)

$800.00

Bags Needed by Size

40 lb

480

60 lb

320

80 lb

240

What Is Concrete Made Of?

Concrete is a composite material made from coarse and fine aggregates (gravel and sand) bound together by cement paste, which hardens through a chemical reaction with water rather than by simply drying out. Fresh concrete must be placed and finished before it hardens — typically within about 90 minutes to 2 hours depending on the mix and temperature.

Concrete gains strength gradually as it cures: it's generally safe to walk on after about 24-48 hours, but reaches around 70% of its final strength after 7 days and doesn't reach over 90% of its full strength until roughly 28 days after pouring.

Concrete Needed by Slab Thickness

For your 288 sq ft area, here's how much concrete different thicknesses require.

Thickness Cubic Yards 80 lb Bags
4" 3.556 160
5" 4.444 201
6" (yours) 5.333 240
8" 7.111 321
10" 8.889 400

How Is Concrete Volume Calculated?

Volume is simply length × width × thickness, with thickness converted from inches to feet first. The result in cubic feet is then divided by 27 to convert to cubic yards, the unit ready-mix concrete is typically sold and priced in.

Volume (cu ft) = Length × Width × (Thickness ÷ 12) Volume (cu yd) = Volume (cu ft) ÷ 27

Bagged Concrete vs. Ready-Mix Delivery

Small projects (under about 1 cubic yard) are usually most economical with bagged premix concrete — an 80 lb bag yields about 0.6 cubic feet of concrete once mixed with water. Larger pours are typically cheaper and far less labor-intensive with a ready-mix truck delivery, priced per cubic yard.

Choosing the Right Thickness

4 inches is the standard thickness for patios, walkways, and shed foundations under normal residential loads. Driveways handling vehicle weight, especially larger trucks, typically need 5-6 inches or more, and often benefit from steel reinforcement (rebar or wire mesh) to resist cracking.

Always Buy a Little Extra

Uneven ground, spillage, and small measurement errors mean actual concrete needs often run 5-10% higher than the calculated volume — many contractors round up to the next whole bag count or full cubic yard delivery to avoid a costly mid-pour shortage.

Example — Your Current Inputs

A 12 × 24 ft slab at 6" thick needs 5.33 cu yd of concrete (144.0 cu ft), weighing about 10.80 tons — that's 240 bags of 80 lb premix. By the cubic yard, that costs about $800.00.

Additional Example — A Shed Foundation

An 8 x 10 ft shed foundation poured 4 inches thick needs about 0.99 cubic yards of concrete — roughly 45 bags of 60 lb premix, or one small ready-mix delivery if a supplier's minimum order allows it.

About These Parameters

Length & Width
The slab's footprint dimensions in feet. Multiply these together for the total area before applying thickness.
Thickness
The depth of the pour in inches. Thicker slabs use volume (and cost) proportionally — doubling thickness exactly doubles the concrete required.
Premix Bag Size & Price per Cubic Yard
Bag size only affects the bag-count estimate for DIY mixing. Price per cubic yard is optional, used only if you're pricing out a delivered ready-mix order instead.

Frequently Asked Questions

How many 80 lb bags are in a cubic yard?

About 45 bags of 80 lb premix are needed to make one cubic yard of concrete, since each bag yields roughly 0.6 cubic feet and a cubic yard contains 27 cubic feet.

Should I add extra for waste?

Yes — most contractors add 5-10% extra to account for uneven subgrade, spillage, and measurement variance, then round up to the nearest full bag count or delivery minimum.

When is ready-mix delivery worth it over bags?

Once a project needs more than about 1 cubic yard, ready-mix delivery is usually cheaper per unit of concrete and dramatically less labor than hand-mixing dozens of bags — though many suppliers have delivery minimums, so check locally.

Other Slab Sizes

See also